Roads Sanctioned under PWRD (ASRP)
List of Roads Sanctioned under PWRD, Assam State Roads Project (ASRP), Assam
Improvement & Upgradation work Packages, Year: 2013 - 2018
SL. No.
Name of Road
Length of Road work in (km)
Nos. of Bridges Sanctioned
Sanctioned Amount in Lakhs
Status
1.
SH-2 (Manas river to Beki river & Jania Bazar to Barpeta Medical College)
21.84
12,619.56
Work in progress
2.
SH-2 (Beki River Missing Link)
5.00
Work in progress
3.
SH-2 (Barpeta Medical College to Barpeta Town)
1.93
1
2,631.44
Work in progress
4.
SH-2 (Chapaguri - Manas River Road)
31.29
2
16,545.44
Work in progress
5.
SH-46 (Dudhnoi - Matia Junction)
8.90
5
17,197.31
Work in progress
6.
SH-46 (Matia Junction - Dubapara)
12.25
Work in progress
7.
SH-46 (Dubapara - Goalpara BOC)
10.25
Bid Evaluation under process
8.
SH-46 (Goalpara ASTC Bus Stand - Pancharatna)
9.82
1
Work in progress
9.
SH-3 (Narengi - Bonda)
2.00
2
2,539.13
Work in progress
10.
SH-3 (Morigaon - Kumargaon)
12.60
10,823.23
Work in progress
11.
SH-3 (Kumargaon - Nomatigaon)
12.53
Work in progress
12.
SH-3 (Nomatigaon - Nagaon)
10.00
Work in progress
13.
SH- 3 (Nagaon-Palakhani)
8.00
9,493.67
Work in progress
14.
SH-3 (Palakhani-Singimari)
10.47
Work in progress
15.
SH-3 (Singimari - Naltoli)
22.02
3
8,873.30
Work in progress
16.
SH-45 (Soibari - Itakhola & Borpam - Sapekhaiti)
10.90
1
3,735.95
Work in progress
17.
SH-31 (Jorhat - Morioni)
17.35
7,529.41
Work in progress
18.
SH-32 (Borhola-Mokrom)
4.70
1
4,256.59
Work in progress
19.
SH-32 (Mokromla-Goronga)
7.83
1
Work in progress
20.
SH-22 (Gogamukh - Ghilamara)
22.07
1
9,378.48
Work in progress
21.
SH-42 (Ghilamara - Dhakuakhana)
16.04
3
6,889.37
Work in progress
22.
SH-45 (Itakhola - Borpam)
10.11
1,945.40
DPR under preparation
Total
267.91
114,458.28